Unfortunately, this important technique tends to make projects longer, not shorter
Looking at the plans produced by critical path analysis, we might realise the same person is scheduled to undertake two or more tasks simultaneously
Question: How can we solve this? How can we minimise the impact on the completion date?
The following tasks should be delayed
Consider also reallocating tasks to other team members so there is no overload
Before resource smoothing. (Underlined tasks are on the critical path)
| Effort | B | B | ||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| A | A | A | A | C | D | D | D | |||
| Time | ||||||||||
Print this page and enter your solution here:
| Effort | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|
| Time | ||||||||||
|
|